Superintendent » Facility Plan

Facility Plan

2024-2025

Campus

Current Enrollment

Current Capacity

% Growth to Capacity

Maximum Capacity

Partin Elementary

483

675

28%

675

Sanford Elementary

562

800

30%

800

Middle School

433

660

34%

660

Junior High

405

800

49%

800

High School

729

1100

33%

1100

District

2512

4050

38%

4050


The chart above indicates present levels at all campuses. 

Van Alstyne ISD has contracted with Zonda Demographics to study growth patterns within the district. This analysis is done twice a year in order for the district to plan for growth. The chart below is extracted from the study. Yellow indicates capacity.

Campus

2024/25

2025/26

2026/27

2027/28

2028/29

2029/30

2030/31

Partin

483

542

602

664

711

792

879

Sanford

562

600

623

690

747

801

853

Middle

433

481

559

598

653

717

759

Jr High

405

461

515

565

658

704

768

High

729

791

831

917

997

1114

1270

District

2512

2875

3130

3434

3766

4128

4529


Facility Plan

Elementary

A site for a new elementary on the West side of I-75 was acquired in the Mantua subdivision. With current growth projections, a new elementary will be needed by 2026 – 2027 school year. This building is currently under construction. 

With the construction of the new high school, the elementary campuses became Pk-4 campuses.  Moving the 5th grade back to an intermediate campus (5/6) added 20% capacity back to the current campuses. 

Middle School

The middle school will reach its core capacity in the 2028/29 school year, which will facilitate a need to build a second Junior High.



Junior High

Land for a new junior high has been purchased. Design needs to begin by summer 2026. Moving the 6th graders to the new Junior High will add 47% capacity back to the middle school. A new junior high needs to be operational by 2029 at current growth rates.

High School

The high school will reach its core capacity by the 2028 - 2029 school year. Planning has begun on phase 2 which will add capacity of 500 students to the high school. Construction should begin by the end of the year 2025 in order to have it open for future growth. An auditorium and indoor facility are still in the bond package and have been designed when the money is available for construction.

Admin/Maintenance/Transportation

The administration building along with maintenance and transportation is reaching capacity in the current facility. The district needs to look at options to build a transportation/maintenance hub at the old maintenance area. The district should also determine if a new administration building would be beneficial for long term growth.

 